Microsoft Project

How to Create a Hammock Task in Microsoft Project

This post details a procedure for creating a Hammock Task in Microsoft Project. A Hammock Task is a Task parallel to another set of Tasks but one that is constrained to have their same total Duration, no matter how that changes. It will have an “elastic” Duration.

A Useful Example of the Hammock Task in Microsoft Project

We have an engineer working for 8 days starting on Monday. He/she will be staying in a hotel during the weekend. If the engineer starts work on Thursday, we will have 2 weekends. Also, if the duration of his/her work might change, so the number of weekends cannot be known in advance. We need a solution that allows us to charge hotel nights for all calendar days no matter what the duration or the start date of the engineer’s task is. Solution: Hammock Task.

Reverse Engineering the Work Formula in Microsoft Project

At the heart of planning a project using Microsoft Project is the daunting responsibility of assigning Resources to Tasks. Worse still, try adjusting those assignments (both during planning and monitoring) and see what happens.
A confusing facility in Microsoft Project is the way Duration, Units of Resources and Work Loads per Task are interact with one [...]